A range of solutions to optimise processes, assets and infrastructure
Power continuity when the grid fails: diesel gensets up to 4,000 kW and gas gensets (methane, propane-butane), hybrid photovoltaic systems and UPS. It includes fuel storage and pumping under fire service and SENCAMER requirements, which is where most projects get stuck at inspection.
Units up to 4,000 kW, single or in parallel, with synchronisation and load sharing. Gas engines (methane or propane-butane) where that fuel is easier to get than diesel.
ISO 8528 · NFPA 110
Day and bulk tanks, transfer system, secondary containment and leak detection, to fire service and SENCAMER requirements.
NFPA 30
Automatic transfer switchboards with switching times matched to how critical the load is, and interlocks that prevent accidental paralleling with the grid.
Generación solar combinada con banco de baterías y respaldo de planta, y UPS para la carga que no tolera ni un ciclo de interrupción.
IEC 62040
Fuel level, running hours, start status and genset faults reported remotely. It prevents the classic case: the genset that will not start the day the power goes, because it had been without fuel for months.
We build medium voltage lines and networks (13.8 kV and 34.5 kV), overhead and underground, from the CORPOELEC point of connection to the client's transformer bank. We deliver the whole job: feasibility, engineering, permits, procurement, construction, testing and handover.
Concrete or steel poles, crossarms, insulators and guys; bare ACSR/AAAC conductors or covered cable for urban and tree-lined areas. Switches, cut-outs, surge arresters and pole-mounted transformer banks.
ANSI C2 (NESC)
Ducting in PVC DB-120 or HDPE conduit in a concrete duct bank, pull and splice manholes, 15 and 35 kV XLPE/EPR cables, premoulded terminations and pad-mounted transformers.
IEC 60502-2
Service feasibility, project approval, inspection and handover. This is the procedure that delays a project most when the contractor does not know it; we handle it end to end.
Soil resistivity and ground resistance, insulation testing, VLF on the medium voltage cables, thermography and an energization protocol.
IEEE 400.2 · IEEE 81
Where the project allows, the same trench carries both the power network and the fiber, respecting the clearances of the National Electrical Code. It saves civil works and time.
For when the installation has outgrown its service entrance: phase balancing, raceway upgrades, transformer capacity increases and feasibility studies, with the CORPOELEC permitting. Before proposing more capacity we measure the actual demand: often the problem is not a lack of power but an imbalance or a penalised power factor.
Load curve logging over a representative period to establish peak demand, utilisation factor and phase imbalance, before deciding how much to upgrade.
IEEE 1159
Redistributing single-phase loads across the three phases. In many installations this frees enough capacity without touching the transformer.
Transformer replacement or addition, new feeders and switchboard upgrades, with an updated short-circuit study.
IEC 60076
Load increase request to CORPOELEC, project approval and handover of the works.
Once upgraded, continuous measurement shows whether the installed capacity is actually being used or whether the projected growth never arrived.
A proprietary system that protects the critical load against overvoltage, harmonics and blackouts. It came out of a recurring problem in Venezuela: expensive equipment — chillers, lifts, air handling units, servers — damaged by the quality of the grid rather than by any fault of its own. SIPAVVO disconnects before the damage happens and reconnects when the grid returns to range.
It disconnects the load when voltage leaves the set window (typically ±30% of nominal) and restores it with a delay that avoids repeated restart cycles.
Surge arresters rated in kA for lightning and switching events, coordinated with the service entrance protection.
IEC 61643-11
It de-energises the load outside working hours. At Torre Nordic this extended the service life of chillers and lifts by more than 50%, on top of the energy saved.
Air handling units, chillers, lifts, pumps, data centres and any load whose replacement cost comfortably exceeds the cost of protecting it.
A log of every disconnection event with its cause and duration. It gives you hard evidence to claim against the utility or to justify investing in backup.
Technical advisory to decide before investing: audits of existing installations, expert assessment after a failure, feasibility studies, technical specifications for tendering and supervision of works built by third parties. After more than three decades of building, we know where the problems usually are.
Review of compliance with the National Electrical Code, switchboard thermography, condition of protection and grounding, with findings ranked by risk.
NFPA 70B · COVENIN 200
Root cause determination after an event: fire, equipment damage or extended outage, with a report that can be used with the insurer.
Technical and financial assessment before committing the investment: how much capacity is needed, what the regulator requires and what it actually costs.
Drafting tender documents and supervising third-party works, checking that what was built matches what was contracted.
Supply, lifting, installation and commissioning of diesel gensets with a 20,000-litre storage system.
Supply, installation and commissioning of diesel gensets with 10,000 litres of fuel storage.
SIPAVVO protection system for 19 air handling units, each independently protected against voltage variations.
SIPAVVO with time-of-day control for chillers and lifts. It extended equipment life by more than 50%.
Electrical energy metering modules with remote telemetry: kWh, frequency, current and voltage.







From generators to SIPAVVO protection. Request a technical visit with no obligation.